Legionella After a Shutdown: Reopening a Building
Water that stands still in a closed building is where legionella grows. For a closure of a week or two, every outlet left unused for seven days or more is flushed before anyone uses it. A building, floor or system taken out of use for longer is left full of water. Before it is used again, HSE guidance says it should be "recommissioned as though they were new".
The work is easiest if it is planned before the doors shut. Below: why a closure is a risk, and what to do for a short break and a long one. Then what recommissioning involves, the rule for cooling towers, and what to record.
Need a risk assessment before you reopen? A fixed price within one working day.
Closures at a glance
| Closure | What HSE guidance says | Where |
|---|---|---|
| Any outlet unused for seven days or more | Flush it weekly, or as the risk assessment says, until the temperature settles | HSG274 Part 2, Table 2.1 |
| A building, floor or system taken out of use | Leave it filled with water, not drained down | HSG274 Part 2, 2.52 |
| Before it is used again | Recommission it as though it were new: flushed, cleaned and disinfected | HSG274 Part 2, 2.52 |
| A cooling tower shut for a month or more | Inspect, disinfect and if need be clean it before it runs | HSG274 Part 1, 1.82 |
City & Guilds qualified, LCA registered assessors · Report usually within 10 to 15 working days of the visit
Why a closed building is a risk
In a building in use, water moves every day. Each time a tap runs, the water in the pipe is replaced with fresh, cold water from the mains or hot water from the heater. Close the building and that stops. The water in every pipe, tank and shower hose sits still and drifts towards room temperature. That is the 20 to 45°C range in which legionella grows.
HSE guidance is clear about how risky that gap is. It is writing about a new building, filled with water before people move in. The time between filling the system and normal use, it says, "is potentially the most hazardous". A building that has been closed is in the same position when it reopens.
The first person to run a shower after the break breathes in whatever grew in that pipe while nobody was there. That is why the flushing comes before people use the outlets, not after.
A short closure: Christmas, half term, the summer
For a closure of a week or two, the rule is the same one that covers a quiet tap all year round. HSE guidance puts on the flushing list anything "not used for a period equal to or greater than seven days". It says to flush it weekly, or as the risk assessment says.
In practice, that gives two choices:
- Keep flushing through the closure. Someone comes in once a week and runs every outlet, hot and cold, until the temperature settles. This suits a school over the summer or an office closed for a fortnight.
- Flush everything before people return. For a closure of just over a week, every outlet is run, hot and cold, the day before the building reopens. Start nearest the tank or heater and work outwards.
Keep the hot water on if you can. A cylinder switched off for the holiday cools through the growth range and sits there. Stored hot water should be at 60°C or more. Bringing a cold cylinder back up to temperature, and holding it there before people return, is part of the restart.
How to flush an outlet, step by step, and what to write down, is in our flushing guide.
City & Guilds qualified, LCA registered assessors · Report usually within 10 to 15 working days of the visit
A long closure: mothballing a building or a floor
HSE guidance calls this mothballing. It covers a building, part of a building or a water system taken out of use. It "should be managed so that microbial growth, including legionella in the water, is appropriately controlled".
The instinct is to drain it. HSE guidance says not to: systems "are normally left filled with water for mothballing and not drained down". A drained pipe never dries completely. Pockets of water and damp air stay behind and grow biofilm, and tank joints and metal pipes can fail as they dry.
So the system stays full. The plan for the closed period, regular flushing or treatment, goes into the written scheme with a name against it. Then, before the building is used again, it is recommissioned.
City & Guilds qualified, LCA registered assessors · Report usually within 10 to 15 working days of the visit
What recommissioning involves
HSE guidance says a mothballed system "should be recommissioned as though they were new (ie thoroughly flushed, cleaned and disinfected) before returned to use". What that means depends on the size of the system.
- A small, simple system. HSE guidance covers small developments such as individual commercial or light industrial units and small offices. The water should be "thoroughly flushed before use", as close to people moving back in as possible.
- A larger system. HSE guidance says it should be cleaned, flushed and disinfected to BS EN 806 and BS 8558. A disinfectant such as chlorine is drawn through every part of the system and left for a set contact time. The level is checked at chosen outlets throughout. It is work for a water hygiene contractor, and it is recorded.
- Tanks. A cold water storage tank that has stood is inspected, and cleaned and disinfected if it needs it, before the system is refilled from it.
Will the building fill up slowly? Then HSE guidance suggests leaving parts such as storage tanks out of use until people are there. Early flushing then draws straight from the mains.
Has the building changed while it was closed: rooms removed, a new use, new plumbing? Then its risk assessment is reviewed before it reopens. The HSE says review it whenever there is reason to think it no longer holds.
Disinfection, tank cleaning and other remedial works
City & Guilds qualified, LCA registered assessors · Report usually within 10 to 15 working days of the visit
Cooling towers have their own rule
A cooling tower or evaporative condenser shut down for a month or more is inspected, disinfected and if need be cleaned before it runs again. The same applies before it is first commissioned. In healthcare buildings the trigger is shorter. A tower idle over a long summer or a Christmas shutdown needs this done before it is switched back on, not after.
Plan it before you close
A closure goes smoothly when these are settled before the last person leaves:
- Who comes in to flush, how often, and which outlets. A list by room, so nothing is missed.
- Whether the hot water stays on, and who checks it is back at temperature before reopening.
- For a long closure: who recommissions the system, and when it is booked.
- For a cooling tower: who inspects and disinfects it before it restarts.
- Where it is all recorded, so the log book shows the gap was managed.
All of this belongs in the written scheme, and every flush and check goes in the log book. An inspector reading the record after a closure looks for exactly this.
City & Guilds qualified, LCA registered assessors · Report usually within 10 to 15 working days of the visit
Questions people ask
Do we need to flush the water over the Christmas shutdown?
Yes, if outlets will go seven days or more without use. HSE guidance puts anything "not used for a period equal to or greater than seven days" on the flushing list. Either flush weekly through the closure, or flush every outlet before people come back.
Should we drain the water system while the building is empty?
Usually not. HSE guidance says systems "are normally left filled with water for mothballing and not drained down". A drained system keeps pockets of water and damp that grow biofilm. Leave it full, and recommission it before use.
Should we turn the hot water off while we are closed?
It is better left on. A cylinder switched off cools through the 20 to 45°C range where legionella grows. If it is turned off, bring it back to 60°C or more and hold it there before anyone uses the hot taps.
What does recommissioning a water system mean?
Bringing it back into use as though it were new. HSE guidance says "thoroughly flushed, cleaned and disinfected". For a small, simple system that is mainly a thorough flush. A larger one is disinfected to BS EN 806 and BS 8558 by a water hygiene contractor.
Do we need a legionella test before reopening?
Not automatically. HSE guidance says sampling is for particular cases, such as systems where the controls are not being achieved, or high-risk buildings like care homes. Your risk assessment says whether your building is one of them.
Does the risk assessment need reviewing after a closure?
If the building changed while it was closed, yes: a new use, rooms altered, plumbing added or taken out. The HSE says review it whenever there is reason to think it no longer holds.
Sources
- HSE, HSG274 Part 2: The control of legionella bacteria in hot and cold water systems, paragraphs 2.40, 2.41, 2.43 to 2.45, 2.50 to 2.52 and Table 2.1
- HSE, HSG274 Part 1: Evaporative cooling systems, paragraph 1.82
- HSE, ACOP L8: The control of legionella bacteria in water systems
- HSE, Reviewing what you do
- HSE, Hot and cold water systems
This guide explains legionella legislation and HSE guidance in plain English. It is not legal advice.